Delaware Riverkeeper Network Urges Action to Protect Emerging Amphibians from Pipeline Debacle
Pike County, PA –
According to a letter sent by the Delaware Riverkeeper Network to
multiple regulatory agencies, the delays by the Tennessee Gas Pipeline
to implement mandated restoration for their 300 Pipeline project has
resulted in increased pollution during the time of the delay, and now
threatens to decimate emerging amphibian populations in a number of
wetland areas already damaged by the pipeline company. The Delaware
Riverkeeper Network is therefore urging swift intervention by the
Pennsylvania Department of Environmental Protection and other regulatory
agencies to consider and address the implementation of the long-overdue
wetlands activities in light of new information about impacts to
amphibians. The agencies received a letter from the Delaware Riverkeeper
Network explaining the situation and urging swift intervention to have
the intensive construction activities that are part of the restoration
delayed until the amphibians were mature enough to leave the site.
According to the letter, Tennessee Gas Pipeline has had months to
implement the overdue restoration, the pipeline went into service in
November, and they should not now be allowed to inflict additional harm.
“Had
the Tennessee Gas Pipeline company honored the requirements of their
state issued permits the pipeline would have gone in and associated
environmental restoration would already be complete, allowing us to
avoid sediment and other pollution to local streams and wetlands that
has taken place over the past several months, and avoiding the new
catastrophic threat faced by hundreds, if not thousands, of emerging
amphibians in the process of procreating and developing in the still
disturbed wetlands around the pipeline site,” said Maya van Rossum, the Delaware Riverkeeper.
“Tennessee Gas Pipeline has been irresponsible with how they have
pursued this project, it was their procrastination that has put us all
in this situation. To allow them to now add insult to injury by finally
undertaking their overdue restoration work but at a time when it will
ensure maximum harm to the very ecosystems and species it was supposed
to help would be reprehensible, counterintuitive and counterproductive,”
adds van Rossum.
The Delaware Riverkeeper Network’s Monitoring Director, Faith Zerbe,
discovered the wetlands teaming with wood frogs, American toads and red
spotted newts on a site visit to monitor the ongoing failure of
restoration by TGP earlier this week. “We didn’t do a full
herpetological survey,” Zerbe said, “but we didn’t have to immediately
know the dramatic level of harm TGP would be inflicting if they finally
began their restoration work in this area during this critical period of
reproduction for the amphibians.”
“As
soon as we realized the situation, the Delaware Riverkeeper Network
took immediate action to try to secure protective action by the
agencies,” van Rossum adds.
Also
according to van Rossum, “this is sadly more of the same from Tennessee
Gas Pipeline.” According to a letter sent by the Delaware Riverkeeper
Network to regulatory agencies earlier this year: During the 300 Line
Extension Project, in 28 out of 38 “Environmental Compliance Monitoring
Program Weekly Summary Report[s]” that were provided on FERC’s website,
at least one recorded incident was reported where an activity did not
come into “compliance with Project specifications, mitigation measures,
and applicable FERC-approved Project plans.” Out of 16 inspections
conducted by the Wayne County Conservation District during the 300 Line
Extension Project, violations were found in no less than 15 of the
inspections. The Pike County Conservation District cited numerous
violations during the 300 Line Extension Project including, but not
limited to: 17 instances of dirt and sediment being discharged into
water bodies, 7 violations for worksite conditions, and 21 instances of
failure to properly institute Best Management Practices for erosion and
sediment control.
#####
No comments:
Post a Comment